B12 |
Rocket Garden |
Resting |
Cryo x2, Static fire Jul 15th. Full stack cryo tests Sep 23rd and Oct 7th. FTS installed Oct 9th. Launched as IFT-5 on Oct 13, returned to launch site for successful chopstick catch. Moved to Megabay 1 Oct 15th. |
B14 |
Gulf of Mexico |
Destroyed |
Stacked Apr 26th, Cryo tested Oct 4th and 5th. Static fired Dec 9th. FTS installed Jan 3rd. Wet dress rehearsal performed Jan 10th. Launched and landed Jan 16th. Static fired Apr 3rd. Stacked on launch mount May 13th. Destacked May 16th. Rolled back May 17th. Rolled out May 24th. Launched May 27th. RUD immediately after landing burn startup. |
B15 |
Rocket Garden |
Resting |
Stacked from July to September. Methane tank cryo test Dec 27th, full cryo test Dec 28th. Static fired Feb 9th. Launched and landed Mar 6th. |
B16 |
Pad 1 |
Pending static fire |
Stacking completed by Dec 26th. Cryo tested Feb 28th. Static fired Jun 6th. |
B17 |
Rocket Garden |
Pending engine install |
Parts spotted. First two sections moved to Megabay 1 Jan 4th. Fully stacked by Apr 7th. Cryo tested Apr 9th. |
B18.1 / Test Tank 17 |
Massey's |
Pending cryo test |
Test article for Booster v3. Parts spotted Feb 24th, Apr 21. Cryo tested Jun 2nd and 3rd. |